I am going to build a large brick patio ( 350 sq ft). Since I will only be
able to work on it during weekends. I was planning on doing it in sections.
My thoughts are to excavate the entire area, then pack my base and then put
up screed boards for the sand & leveling. I was going to do it in sections
and leave the screed boards buried in the sand and not remove them. If I
use treated 1x4 it will take quite a while for them to rot. Does anyone see
a problem with doing this? Is there another way to do this in sections over
6-8 weekends?
Thanks
JD